Work has begun to strengthen some of Duke’s Mound arches on the eastern seafront. This has meant traffic can now only enter Madeira Drive from the Palace Pier roundabout and can only exit via Duke’s Mound.
Councillor Trevor Muten, Cabinet member for Transport, Parking and Public Realm, said: “Following our recent announcement of strengthening work to the promenade in front of the Palace Pier, this work to Duke’s Mound is also required because of the increasing number of HGV movements that will use Madeira Drive during the Terrace restoration and seafront works.
“We expect this strengthening work will be finished in April. Once complete, Duke’s Mound will return to two-way traffic.
“Our project team and contractors are doing everything possible to minimise disruption and ensure residents and businesses are kept informed of temporary road or pathway restrictions during this work and the Madeira Terrace restoration.”
A condition survey and structural assessment found that Duke’s Mound had insufficient structural capacity for HGV lorries. Movement and weakness in some of the supporting piers or walls was identified, although the arch barrels were found to be structurally sound.
For these arches to safely carry 40 tonne HGVs, arches 288, 290, 292, 294, 296 and 298 will be filled with foamed concrete. Blockwork walls will be added to the southern façade in each infilled arch, forming a permanent shutter for the concrete. This will be finished with a render coat.
We’ve been in discussion with the existing active tenants of these arches, such as the Martlet Kayak Club and Brighton & Hove Motor Club, who will be relocated to the remaining arches once the strengthening and improvement works are completed.
Councillor Muten added: “We wish to thank residents, local businesses and visitors for their patience as we complete these important safety improvements, strengthening the future for this part of our much-loved seafront.”