Phase 3 will complete the Valley Gardens project with a transformed city centre public space.
The finished scheme will:
Princes Street has now been reopened. In late April/May, work is planned to move north towards Pavilion Street. For some of this time, Pavilion Street will need to be closed. Princes Street will temporarily be made two-way to maintain access.
Construction is also continuing to build a new public space and cycle lane next to the Royal Albion Hotel. A temporary road layout is in place while this work takes place. A temporary pedestrian crossing has also been installed between the Royal Albion Hotel and the eastern side of the Old Steine.
View the construction schedule for Valley Gardens Phase 3.
Construction on the project started in November 2024. So far, we have:
The contractor has set up a compound in Steine Gardens. Once the work is complete, the gardens will be re-landscaped with new grass and planting.
The latest information on the construction schedule will be published here.
The contractor, FM Conway, will provide information to properties ahead of work starting in each section. This will include contact information and they will ensure that access is maintained for residents, customers, deliveries and servicing.
To request future project newsletters, or for any enquiries, send an email to transport.projects@brighton-hove.gov.uk.
View the detailed plan for Valley Gardens Phase 3.
The plan includes:
The council's former Environment, Transport and Sustainability Committee approved the Valley Gardens Phase 3 plan in January 2022.
We've secured £6 million Local Growth Fund (LGF) capital funding from the Coast to Capital Local Enterprise Partnership (LEP). In addition, the council has committed £1.84 million in match funding.
Capital borrowing of up to £5 million will also support the existing funding.
The development of proposals for Phase 3 has been subject to 3 public consultation exercises, and stakeholder design workshops, at key stages of the project.
See the full list of committee reports and minutes related to Valley Gardens Phase 3.