What we’ve done so far
January to December 2025:
- planning preparation
- tender specification
- costs
What we'll do next
January to December 2026 - pre-construction phase, this will include:
- reviewing and consulting with the community stakeholders
- submitting planning
- removing trees from the pond boundary
- procurement
- environmental permits to remove silt
- appointing a contractor
January to December 2027 – construction phase, this will include:
- preparing the construction schedule with the contractor and the community
- delivery and completion
- snagging