Timeline of work
We’ll share progress reports on this page as we move forward with the project.
- September 2025 – Site fencing in place to keep site safe.
- October - November 2025 – Access improvements made to footway paths and crossing.
- November 2025 to January 2026 – Preparation for soft landscaping, including moving palms.
- January to March 2026 – Soft landscaping work carried out to reshape the flower beds.
- March 2026 – Planting new flower beds.
- April to May 2026 – fencing remains in place so the plants until plants and lawn are established.
- May 2026 – Public consultation on the future of the Floral Clock feature.